The common mistake with a snagging list template is waiting for the customer to write it. If the first list of faults on a job is theirs, it arrives as a long text a week after you've left, mixing real defects with things you never quoted for, and the final payment waits while you argue about which is which.
Walk the job yourself before handover, then walk it again with the customer, using one list you both sign. Below is a snagging list to print or copy, how to write each snag so it gets fixed first time, what the law says about putting faulty work right, and a worked example from a kitchen extension. It suits builders, joiners, plumbers, electricians, roofers and anyone handing back a finished room. For the rest of the job record, see the guide to running and recording trade jobs.
A snagging list to print or copy
Use the list below on paper, as a page in your job app or as a shared document the customer can see. Fill in the top before you start the walk, one block per snag as you go, and the sign-off at the end.
Type is one of five: defect, unfinished, damaged, change or not ours. The table further down says what each means and who pays. Number your photos to match the snag, so photo 4 shows snag 4.
Walk the job yourself before the customer does
Do your own walk-round a day or two before handover, with the list, a torch, a roll of low-tack masking tape and a phone. You're looking for anything the customer will see in the first week: paint on glass, a door that catches, a gap where the sealant stopped short, a socket faceplate fitted crooked, a tap that drips, a cupboard that won't close square.
Look at each room in a set order, so nothing gets skipped. Start at the door, go round the walls clockwise at eye level, then low down, then the ceiling, then the floor, then everything that moves or runs: doors, windows, drawers, taps, switches, radiators and extractor fans. Run the water, flush the toilet, open every window and switch everything on. A fault you find by trying it costs a few minutes to fix while you're still there. The same fault found by the customer costs a return trip.
Mark each snag with a small strip of tape and write it on the list straight away. The tape tells whoever does the fix where to look, and when it comes off you know that one's done. Fix what you can on the day, tick it on the list, and leave the rest with a name and a date.
This first walk is your own work, so be harder on it than the customer would be. Every snag you clear before handover is one that never reaches their list, and a short customer list is the quickest way to the final payment.

Walking the snags with the customer
Book the walk-round as part of the handover, not as an afterthought. Tell the customer when you agree the finish date: "Before we finish, we'll walk round together with a snagging list, put right anything we've missed, and you sign it off." A customer who knows that walk is coming tends to save their points for it, rather than texting them one at a time.
Walk in daylight if you can. Artificial light hides marks on paint and plaster that show up the next sunny morning, and the customer will see them then. Take the same route you took on your own walk, and let the customer lead the pointing. Your job on this walk is to listen, look and write, not to explain why something is fine.
Write down everything the customer raises, even if you think it isn't a fault. If it isn't, the list is where you say so, with the type marked. A point left off the list doesn't go away; it comes back later as a complaint you have no record of.
Agree a fix-by date for each open snag before you leave, and say who's coming. "Snag 3, Thursday morning, Kofi" is a promise the customer can hold you to, which is why it works. Leave the customer a copy, by photo or email, the same day.

Write each snag for whoever fixes it
A snag has to make sense to someone who wasn't there. The joiner who comes back on Thursday may not be the one who walked the job, and the customer may read the list again a month later. Each line needs three things: the exact spot, the fault, and the finished result.
Where means the room and the spot: "Kitchen, left-hand wall cupboard above the hob, bottom hinge", not "kitchen cupboards". If the room has more than one of something, count from the door, or use the plan's numbers. Write what's wrong as a fact you can see or measure: "door drops 3mm at the handle side and rubs the next door", not "door not right". Done is the result: "doors level and both close without touching".
Avoid words that mean different things to different people. "Tidy up", "make good" and "finish properly" all lead to a second visit, because the person fixing it and the customer each picture something else. If you'd need to point to explain it, describe what you'd point at.
One fault per line. "Bathroom: grout, sealant and the towel rail" is three snags with three different fixes, and possibly three different trades. Split them, so each can be ticked off when it's done, and the list shows how many are left.
Two more, written both ways. "Paint needs touching up" becomes "Lounge, wall behind the door, about 1m up: scuff 10cm long through to plaster; done when repainted to match, with no line visible in daylight". "Bathroom sealant" becomes "Bathroom, bath to tiled wall, tap end: sealant stops 15cm short of the corner; done when sealed corner to corner".
Photograph every snag before and after
Take a photo of every snag, at the moment you write it down. Stand back for the first photo, so the room and the spot are clear, then go close on the fault. Put the snag number in the photo if you can, on the tape or a scrap of card, so it can't be matched to the wrong line.
Take the after photo too, once the snag is fixed, from the same spot. A before and after pair is the simplest proof that a point was dealt with, and it saves an argument if the customer says later that it never was. Keep both photos with the job, not just on the engineer's phone, so the office can see them when the final invoice goes out.
Put the quote and job references at the top of the list. When a customer says something wasn't done, the first question is whether it was in the quote. With the reference on the list, you or the office can open the quote and check in a minute. Our quote template for trade work numbers each task, so a snag can say "Task 4, skirting to kitchen" and there's no guessing what was agreed.
The same goes for the job sheet. If an engineer noted on the day that a wall was out of true, or that the customer chose to keep an old radiator, that note answers the snag before it becomes a dispute. Our job sheet template for trade visits has space for exactly those notes.
Sort each snag by who fixes and pays
Not everything on a customer's list is a fault in your work. Sorting each line by type, as you write it, keeps the conversation about facts rather than feelings. It also tells you who needs to come back.
| Type | What it means | Who fixes it and who pays |
|---|---|---|
| Defect | Your work isn't to the standard you quoted: a leak, a crooked tile, a door that sticks | You fix it, at your cost, within a reasonable time |
| Unfinished | Something in the quote isn't done yet: a missing plinth, a cover plate not fitted | You finish it, at your cost, by an agreed date |
| Damaged | Something got marked or broken during the job, by you or another trade | Whoever caused it, if known; if not, agree it before you leave |
| Change | The customer wants something different from what was agreed | A priced extra, agreed in writing before you do it |
| Not ours | The item isn't part of your job: old plaster, another firm's window, the customer's own fitting | Note it on the list and offer to quote if you can do it |
Be fair with the types. Marking a real defect as "not ours" will cost you more in goodwill than the fix would, and a customer who sees you own the defects is more likely to accept a "not ours" when it's true. If you aren't sure whether something was in the quote, check before you answer.
What the law says about faulty work
When you do work for a homeowner or other consumer, the Consumer Rights Act 2015 sets the standard. Section 49 says every contract to supply a service includes a term that the trader must perform the service with reasonable care and skill. A snag that's a defect in your work is the kind of thing that falls short of that.
If the work isn't up to that standard, section 55 gives the customer the right to require you to do it again or put it right. You must do that within a reasonable time and without significant inconvenience to the customer, and you pay the costs of doing so, including labour and materials. A snagging list with a fix-by date for each defect is a practical way to show you're meeting that.
If putting it right is impossible, or you don't manage it in a reasonable time without significant inconvenience, section 56 gives the customer the right to a price reduction. Any refund under that section must be paid within 14 days of the day you agree the customer is owed it. That's the risk of leaving snags open: the customer can stop waiting and ask for money off instead.
Citizens Advice tells homeowners in England that problems should be fixed within a reasonable amount of time, without causing them too much inconvenience, and that they should ask the trader to put it right first, and can ask for a partial or full refund if the trader can't or won't. It also tells them to gather their paperwork, take photos of the problem and note what happened with dates and times. A customer following that advice is building a record of the job. Your snagging list, with its photos and dates, is yours.
The snagging walk and the signed list are good practice, not a legal requirement, and a signature records what you both saw on that day. Write the sign-off as that record, and don't word it as a promise that nothing else will ever be raised.
These sections of the Consumer Rights Act cover work for consumers across the UK: England, Scotland, Wales and Northern Ireland. Citizens Advice has separate pages for Scotland, Wales and Northern Ireland. Work for a builder, a landlord's company or another business is under different rules, so check your contract with them. This is not legal advice. It summarises the Act and the Citizens Advice guidance linked here. If a snag turns into a dispute, get advice before you refuse to put it right.
Worked example: a kitchen extension handover
This is an invented example to show the list in use. The names, figures and job are made up, and the figures are not a guide to what building work costs.
Illustrative example: snagging a kitchen extension before the final payment
Job: single-storey kitchen extension, 14 Larch Close; quote Q-208, fixed price £24,000; stage payments to date £22,800; final payment £1,200 due on sign-off
Own walk-round: Tuesday, by Mei Lin (builder); 9 snags found, 7 fixed the same day, 2 left with dates
Customer walk-round: Thursday, with Mr Hale; 5 points raised
Snag 1: utility doorway, frame top: 4mm gap above door; defect; joiner Kofi; fix by Monday
Snag 2: skirting, left of bifolds: scuffed through to wood; damaged by our team; Mei; fix by Monday
Snag 3: worktop end by fridge: sealant stops 10cm short; unfinished; Mei; fixed on the day
Raised, not ours: crack in the old hallway ceiling, outside the quote; noted and photographed, offered to quote
Raised, change: move one double socket 30cm along; priced as variation V3, £95, approved by text
Sign-off: Monday; snags 1 to 3 closed with after photos; customer signed; final £1,200 invoiced that day, V3 invoiced separately
Mei found most of the snags herself on Tuesday, so Mr Hale's list on Thursday had five points, not fourteen. Two of those were defects or damage, and she gave a name and a date for each. The ceiling crack was outside the job, and the photo and note on the list settled it there and then. The socket was a new request, so it went on a variation with its own price rather than becoming a free extra hidden inside the snags.
On Monday, with every snag closed and photographed, Mr Hale signed the list and the final £1,200 was invoiced the same afternoon. If the list had gone round by text instead, the socket, the ceiling and the scuffed skirting would have been mixed into one message, and the final payment would have waited until it was sorted out.
Extras and customer changes on the snagging list
A snagging walk is where customers often think of something new. They see the finished room and want the socket moved, the shelf higher or a different colour on one wall. None of that is a snag, and putting it on the list as one is how jobs drift past their finish date while the final payment waits.
When it happens, write it in the "not part of our work" section, mark it as a change, and offer to price it. Then deal with it as a variation: a short written description, a price, and the customer's approval before you start. Our variation form template for trade jobs sets out those lines and keeps a log you can copy onto the invoice.
Keep the two apart on the invoice too. The snags are included in the price you already agreed, because they're putting your own work right. The changes are extras, each with its own approved price. If they're mixed together, the customer can't tell what they're paying for, and the final payment slows down while they work it out.
Agree the final payment against the signed list
Decide before the job starts how the last payment relates to snagging, and put it in the quote. Many trades hold a small final stage, due once the snagging list is signed off. The customer knows the money is tied to a clear finish, and you know exactly what has to happen before you're paid.
Write it plainly in the quote's payment terms: what the final amount is, and that it's due when the snag list is signed or when the last open snag is fixed, whichever is first. Don't tie it to the customer simply being happy, because there's no date on happy.
Once it's signed, invoice the same day, quoting the job and the sign-off date. If one or two snags are still open and waiting on a part, agree with the customer whether the final payment waits or whether they hold back a small amount until those are done, and write that on the list. Our invoice template for trades shows how to set out the final invoice, with any variations as separate lines. If you're handing over certificates, instructions and warranty details at the same visit, our guide to the customer handover pack covers what to leave.
Snagging mistakes that drag a job out
Most snagging delays come from how the list is run, not the faults themselves. These are the ones to watch for.
| Mistake | What happens | Fix |
|---|---|---|
| No walk-round of your own | The customer's list is long and the first one they see | Walk it yourself a day or two before handover |
| Snags taken by text, one at a time | No single list, nothing to sign, points keep arriving | Book one walk-round and put everything on one list |
| Vague snag wording | The fix misses, and a second visit is needed | Say where, what's wrong and what done looks like |
| No fix-by date or name | The customer chases, and the snag sits | Give each open snag a name and a date before you leave |
| Changes mixed in with snags | Extras get done for free, or argued about at the invoice | Price each change as a variation |
| No after photo | Nothing to show a snag was fixed | Photograph it from the same spot when it's done |
| Final payment tied to the customer being happy | No clear point when you're owed it | Tie it to the signed list in the quote |
Walk your next finished job with the list
Print the list or copy it into your job app before the next handover. Do your own walk-round first, with tape and a phone, and fix what you can. Then walk it with the customer, sort every point by type, put a person and a day against anything still open, and get the list signed. Count how many points the customer raised that you'd already found: that number tells you whether your own walk is thorough enough.
Find an app for snag photos, then plan the final bill

Trade business software checklist: know what you need before you book a demo
List what a job app has to handle, including snag photos and sign-off, before you pay for one.

How UK trade businesses invoice promptly, set payment terms and chase late payment to get paid faster
Payment terms, invoices and chasing, so the final payment arrives once the snags are cleared.
Sources checked for this guide
The duty to work with reasonable care and skill, and the customer's rights to have faulty work redone or the price reduced, checked against the Consumer Rights Act 2015 and Citizens Advice. These are the primary sources used in this guide.
